Select the date to display on the SmartGantt.
Field/Option | Description |
Scheduled
|
Current dates for the activities as defined in the schedule.
|
Early
|
Earliest possible date that the activity can start.
|
Late
|
Latest possible date that the activity can start.
|
Baseline
|
Dates defined by the project baseline.
|
Original
|
Dates as defined in the schedule prior to any modifications such as acceleration.
|
Px Dates
|
Probabilistic or risk-adjusted dates identified during a project risk analysis.
|